Excel NETWORKDAYS.INTL function
NETWORKDAYS.INTL counts the working days between two dates, both included, with the weekend you choose. Use it for six-day weeks, Friday and Saturday weekends, or part-time staff who work set days. Without a weekend argument it gives the same result as NETWORKDAYS.
=NETWORKDAYS.INTL(start_date, end_date, [weekend], [holidays])Arguments
start_date- The first date. It is counted if it is a working day.
end_date- The last date. It is counted too. If it is before the start date, the result is negative.
weekend- Optional. A code (1 Sat-Sun, 2 Sun-Mon ... 7 Fri-Sat, 11 Sun only ... 17 Sat only) or a string such as "0000011", Monday to Sunday, where 1 is a day off.
holidays- Optional. A range of dates to leave out.
NETWORKDAYS.INTL examples
Every result below was calculated from this sample sheet by the same spreadsheet engine the Cellwise app uses.
| A | B | C | D | E | |
|---|---|---|---|---|---|
| 1 | Period | Start | End | Holiday | |
| 2 | November | Nov 1, 2026 | Nov 30, 2026 | Nov 26, 2026 | |
| 3 | Nov 27, 2026 |
Download this sheet as an Excel practice file (.xlsx)
Result: 21
November 2026 has 21 weekdays, Monday to Friday.
Result: 23
A six-day week with only Sundays off, minus the two holidays: 23 working days.
Result: 8
A part-timer on Tuesdays and Thursdays works 8 days in November.
Result: 22
With a Friday and Saturday weekend the count is 22, because November 2026 has five Sundays and Mondays.
How to use NETWORKDAYS.INTL
- Put the start and end dates in cells.
- Type
=NETWORKDAYS.INTL(start,end,weekend,holidays). - Use a weekend code or a seven-digit string, Monday first.
- Press Enter.
Common NETWORKDAYS.INTL mistakes
Forgetting that both ends count
A Monday to Friday span in one week returns 5, not 4. Subtract 1 if you want days elapsed.
A pattern string without quotes
Type "1010111" with quotes. As a number it is read as a weekend code and returns #NUM! unless it happens to be valid.
Holidays on days off
A holiday that falls on a weekend day is not subtracted again, so it does not change the count. That is correct, not a bug.
NETWORKDAYS.INTL FAQ
How do I count working days with a Saturday working week?
Use weekend code 11, Sunday only: =NETWORKDAYS.INTL(start,end,11,holidays).
How do I count how many Mondays are in a month?
Use a string that marks every day except Monday as off: =NETWORKDAYS.INTL(start,end,"0111111").
What is the difference between NETWORKDAYS and NETWORKDAYS.INTL?
NETWORKDAYS always treats Saturday and Sunday as the weekend. NETWORKDAYS.INTL lets you choose the weekend days.