Free project status report template

For project managers who send a weekly status report and want the RAG to follow from the numbers instead of from the mood of the week. Enter the budget, spend, % complete and your milestones with baseline and forecast dates, and the template works out slip in working days, cost performance, a forecast final cost, and schedule, budget and overall RAG, plus a one-line headline to paste into the email.

cellwise-project-status-report.xlsxExcel workbook · 4.6 KB · works in Excel, Google Sheets, Numbers and LibreOffice · no signup
Download free template

Preview and try it

This is the template's sheet, calculated by the same engine as the Cellwise app. Change any number to see the formulas react before you download.

ABCDEF
1Weekly project status
2ProjectWebsite relaunch
3Status dateNov 2, 2026
4Budget31920
5Spent to date17005
6Work complete (hours-weighted)0.47
7HolidaysNov 26, 2026Nov 27, 2026
8
9MilestoneBaseline dateForecast dateDone?Slip (working days)Status
10Requirements signed offOct 9, 2026Oct 9, 2026Yes0Done
11Wireframes approvedOct 23, 2026Oct 23, 2026Yes0Done
12Design sign-offOct 30, 2026Nov 6, 2026No5At risk
13Content completeOct 30, 2026Nov 11, 2026No8Slipping
14Site build completeNov 25, 2026Nov 30, 2026No1At risk
15LaunchDec 8, 2026Dec 10, 2026No2At risk
16
17
18Budget used0.53273809524
19Cost performance index (CPI)0.88
20Forecast cost at completion36273

How the formulas work

Slip in working days

E13=IF(B13="","",IF(C13>B13,NETWORKDAYS(B13,C13,$B$7:$C$7)-1,-(NETWORKDAYS(C13,B13,$B$7:$C$7)-1)))

NETWORKDAYS counts both end dates, so subtract 1 to get the gap. The holidays in B7:C7 are skipped: content complete moves from Friday October 30 to Wednesday November 11, which is 8 working days late. A forecast earlier than baseline shows as a negative number.

Milestone status

F13=IF(B13="","",IF(D13="Yes","Done",IF(C13<$B$3,"Missed",IF(E13>5,"Slipping",IF(E13>0,"At risk","On track")))))

Done first, then Missed if the forecast date has already passed without the milestone being done (update the forecast!), then Slipping for more than 5 working days late, At risk for any slip, otherwise On track.

Cost performance index

B19=IF(B5>0,ROUND(B6*B4/B5,2),0)

Earned value (the share of work done times the budget) divided by what you have spent. 0.88 here: 53% of the budget is gone for 47% of the work. B6 should be weighted by effort, not a simple average of task percentages.

Overall RAG from the parts

B25=IFS(OR(B23="Red",B24="Red"),"Red",OR(B23="Amber",B24="Amber"),"Amber",TRUE,"Green")

The overall status is the worst of schedule and budget. Schedule is Red when any milestone is slipping or missed; budget is Red when CPI drops under 0.9 and Amber under 0.97. Change the thresholds in B23 and B24 to the ones your sponsor agreed.

A headline for the email

B26="Overall "&B25&": "&B21&" milestone(s) slipping, "&TEXT(B18,"0%")&" of budget used for "&TEXT(B6,"0%")&" of the work"

TEXT formats the percentages inside the sentence. Paste it as the first line of your status email so readers who stop there still get the point.

Make it yours

FAQ

What should a weekly project status report include?

An overall RAG with one sentence of why, milestones with baseline and forecast dates, budget used against work done, the top risks and issues with owners, and any decisions you need from the reader. Keep it to one page.

What does a CPI of 0.9 mean?

For every dollar spent, the project has delivered 90 cents of planned work. If performance stays the same, the final cost will be about the budget divided by 0.9, or 11% over.

Can I use WORKDAY instead of NETWORKDAYS?

They answer different questions. NETWORKDAYS counts working days between two dates (how late is this?). WORKDAY adds working days to a date (if it takes 12 working days, when does it finish?). Both accept a list of holidays.

Functions used