Free project risk register template

For project managers who need a risk log that ranks itself and feeds the status report. List each risk with an owner, a likelihood and an impact from 1 to 5, and the template scores and rates it, counts open high risks and overdue reviews, sets a risk RAG, and fills a 5 x 5 matrix showing where your open risks sit.

cellwise-project-risk-register.xlsxExcel workbook · 4.9 KB · works in Excel, Google Sheets, Numbers and LibreOffice · no signup
Download free template

Preview and try it

This is the template's sheet, calculated by the same engine as the Cellwise app. Change any number to see the formulas react before you download.

ABCDEFGHI
1Risk register
2ProjectWebsite relaunch
3As ofNov 2, 2026
4
5IDRiskOwnerLikelihood (1-5)Impact (1-5)ScoreRatingNext reviewStatus
6R-01Client content arrives lateJon4416HighNov 6, 2026Open
7R-02Key developer unavailable during buildLuis2510MediumNov 9, 2026Open
8R-03Redirects missed, search traffic drops after launchJon3412MediumOct 30, 2026Open
9R-04Stakeholders request new pages after design sign-offMaya4312MediumNov 13, 2026Open
10R-05Hosting migration needs extra security reviewLuis236LowNov 20, 2026Open
11R-06Accessibility issues found late in QAMaya339MediumNov 27, 2026Open
12R-07Stock photo licences not clearedPriya224LowOct 23, 2026Closed
13R-08Brand guidelines change mid-projectPriya144LowNov 30, 2026Open
14R-09Analytics tracking breaks on new templatesLuis326LowNov 25, 2026Open
15
16
17
18
19Open risks8
20Open high risks1

How the formulas work

Score each risk

F6=IF(D6="","",D6*E6)

Likelihood times impact gives a score from 1 to 25. Write down what each number means for your project (for example, impact 5 is "launch slips more than two weeks or costs more than 10% of budget") so two people scoring the same risk land on the same number.

Rate it with IFS

G6=IF(F6="","",IFS(F6>=15,"High",F6>=8,"Medium",TRUE,"Low"))

IFS returns the first rating whose test is true, so the order matters: test for High before Medium. The thresholds here (15 and 8) are a common starting point; change them to match your organization's risk policy.

Reviews that are overdue

B22=COUNTIFS(H6:H17,"<"&B3,I6:I17,"Open")

Counts open risks whose next review date is before the as-of date in B3. A register nobody revisits is worse than none, because it gives false comfort. Here one review is overdue: the redirects risk was due for review on October 30.

One RAG for the status report

B23=IFS(B20>0,"Red",B21>0,"Amber",TRUE,"Green")

Any open High risk makes the register Red, any open Medium makes it Amber, otherwise Green. The sample is Red because "Client content arrives late" scores 16.

The 5 x 5 risk matrix

E27=COUNTIFS($D$6:$D$17,$A27,$E$6:$E$17,E$26,$I$6:$I$17,"Open")

Each cell counts open risks with that likelihood (the row) and impact (the column). The mixed references ($A27 and E$26) let one formula fill the whole grid. Shade the top-right corner red in Home > Conditional Formatting to turn it into the familiar heat map.

Make it yours

FAQ

What should a risk register include?

At minimum: an ID, a clear description, an owner, likelihood and impact scores, a resulting rating, the planned response, a next review date and a status. Many teams also log the trigger that would show the risk is happening.

What is the difference between a risk and an issue?

A risk might happen; an issue is already happening. When a risk occurs, close it in the register and log it as an issue with an action and an owner.

How do I color the risk matrix in Excel?

Select the matrix cells and use Home > Conditional Formatting > New Rule. A common approach is to color each cell by its position (likelihood x impact) rather than by its count, so the high-score corner is always red even when it is empty.