For contractors who want to know mid-job, not at the end, whether a job is still making money. List each cost code with its original budget and any change order cost, enter what you have spent and your best estimate of what is left, and the template projects the final cost for every line, flags the lines heading over, and shows projected profit against the revised contract.

cellwise-construction-job-costing.xlsxExcel workbook · 4.6 KB · works in Excel, Google Sheets, Numbers and LibreOffice · no signup
Download free template

Preview and try it

This is the template's sheet, calculated by the same engine as the Cellwise app. Change any number to see the formulas react before you download.

ABCDEFGHIJ
1Job cost report
2JobKitchen remodel, job 26-118
3Contract price48500
4Approved change orders (billed)3250
5Revised contract51750
6
7CodeCost itemOriginal budgetChange order costRevised budgetActual to dateEst. to completeProjected finalOver / underStatus
801Demo and disposal240002400265002650-250Over
902Framing and blocking310045035503320200352030OK
1003Plumbing (sub)680012008000590020007900100OK
1104Electrical (sub)52008006000410017005800200OK
1205Drywall and paint340003400120021003300100OK
1306Cabinets9800098009800098000OK
1407Countertops460004600049504950-350Over
1508Tile and flooring39000390060032003800100OK
1609Supervision and cleanup180001800950800175050OK
17Total41000245043450285201495043470-20
18
19Projected cost43470
20Projected profit8280

How the formulas work

Revised budget includes change orders

E8=C8+D8

Approved change orders add scope, so the cost side of each one raises that line's budget. Plumbing went from $6,800 to $8,000 after a $1,200 change order. Track the price you billed the client for change orders in C4, so the revised contract in C5 grows too.

Projected final cost

H8=F8+G8

What you have spent plus what you still expect to spend. Actual to date alone makes a half-finished job look great; adding the estimate to complete shows where it will land. Update column G every week from the foreman's count of what is left.

Over or under, per line

I8=E8-H8

Revised budget minus projected final. Positive is money left over, negative is an overrun. Column J turns it into Over or OK, and C22 counts the lines over. In the sample, demo and countertops are both heading over.

Projected profit and margin

C20=C5-C19

Revised contract minus projected total cost. The margin in C21 divides it by the revised contract. Compare it with the margin you bid: if it is sliding week after week, look at the lines in column I first.

Make it yours

FAQ

How do I track job costs in Excel?

Give each cost code a row with budget, change orders, actual to date and estimate to complete. Projected final is actual plus estimate to complete, and budget minus projected final shows whether the line is over or under.

How should change orders be handled in job costing?

Record the cost of the change order against the line it affects, so the revised budget goes up, and record the price billed to the client against the contract. Then profit compares like with like.

What is estimate to complete?

Your best estimate of the cost still to come on each line. It is a judgement, not a formula: ask the people running the work what is left, and update it regularly.