Free project budget vs actual template

For project leads, event committees and team managers who own a fixed budget and need to know where it stands before the invoices all arrive. Enter the budget for each line, what is already committed (signed quotes, purchase orders) and what has been spent; the template shows the variance and % used per line, flags lines that are over or close, totals each category and shows how much contingency is left.

cellwise-project-budget-vs-actual-template.xlsxExcel workbook · 5.7 KB · works in Excel, Google Sheets, Numbers and LibreOffice · no signup
Download free template

Preview and try it

This is the template's sheet, calculated by the same engine as the Cellwise app. Change any number to see the formulas react before you download.

ABCDEFGHI
1Project budget vs actual: regional conference
2Approved budget (excl. contingency)28000Warn at % used0.9
3Contingency (% of budget)0.08
4Contingency amount2240
5
6Line itemCategoryBudgetCommittedSpentSpent + committedVariance% usedStatus
7Venue and room hireVenue650006500650001Watch
8AV equipment rentalVenue180045016502100-3001.1666666667Over
9Catering: lunchesFood4200438004380-1801.0428571429Over
10Catering: coffee and snacksFood90006156152850.68333333333OK
11Speaker feesProgram300015001500300001Watch
12Speaker travelProgram220064019802620-4201.1909090909Over
13Printed programs and badgesMarketing6500712712-621.0953846154Over
14Social adsMarketing12003008801180200.98333333333Watch
15Event app subscriptionTech150001500150001Watch
16PhotographerProgram110000011000OK
17Signage and bannersMarketing80005455452550.68125OK
18Staff travelStaff2400120096021602400.9Watch
19Swag bagsMarketing1400155001550-1501.1071428571Over
20InsuranceAdmin350035035001Watch

How the formulas work

Count committed money, not just what is spent

F7=D7+E7

A signed quote or purchase order is money you will spend even if the invoice has not arrived yet. Adding committed and spent gives the real position of each line. Once an invoice is paid, move the amount from Committed to Spent so it is not counted twice.

Variance and % used

H7=IF(C7>0,F7/C7,0)

Variance in column G is budget minus spent and committed: positive is money left, negative is overspend. % used divides spent and committed by the budget, so 100% is exactly on budget. The IF stops a line with no budget from showing #DIV/0!.

Over and Watch flags

I7=IF(F7>C7,"Over",IF(H7>=$H$2,"Watch","OK"))

Over means a line has passed its budget. Watch means it has used at least the warning level in H2 (90% here) and has little room left. In the sample, five lines are over (AV, lunches, speaker travel, printed programs and swag bags) and six are on Watch. Four of those (venue, speaker fees, event app and insurance) are fixed fees that are exactly 100% used, which is expected; the warning is most useful on lines that can still grow, like staff travel.

Category totals with SUMIF

D24=SUMIF($B$7:$B$20,A24,$F$7:$F$20)

SUMIF adds spent and committed for every line in the category in A24, and column C does the same for the budget. Categories are what a finance team or sponsor usually wants to see; line items are what you manage day to day.

How much contingency is left

D32=SUMPRODUCT((F7:F20>C7:C20)*(F7:F20-C7:C20))

This adds up only the overspend on lines that are over budget. Underspend on other lines is not counted against it, because money not spent yet may still be needed. D33 subtracts the overspend from the contingency in D4 (8% of the budget here). D37 sums up the whole project in one phrase.

Make it yours

FAQ

How do I track budget vs actual in Excel?

List each budget line with its budget and actual spending, subtract to get the variance, and divide actual by budget for % used. Add a status column with IF to flag lines that are over, and SUMIF the lines into categories.

What is the difference between committed and actual costs?

Actual (spent) costs have been invoiced or paid. Committed costs are agreed but not yet paid, such as a signed contract or purchase order. Tracking both shows overspending weeks before the invoice arrives.

Should underspent lines offset overspent ones?

At the very end of a project, the total variance is what matters. During the project, many teams only offset overspend with contingency, because the money left on other lines may still be spent. This template shows both: the total variance in G21 and the overspend against contingency in D32.