Free Excel grant budget vs actual template

For program and grant managers who report spending to a funder. Enter the approved budget for each line and actual spending by quarter; the template totals spending to date, shows what remains, compares the share spent with the share of the grant period that has passed, and flags lines that are running ahead of or behind pace, so you can ask about a budget change before the final report, not after.

cellwise-grant-budget-vs-actual-template.xlsxExcel workbook · 4.7 KB · works in Excel, Google Sheets, Numbers and LibreOffice · no signup
Download free template

Preview and try it

This is the template's sheet, calculated by the same engine as the Cellwise app. Change any number to see the formulas react before you download.

ABCDEFGHIJ
1Grant budget vs actual
2GrantYouth Literacy Program
3Grant startJan 1, 2026
4Grant endDec 31, 2026
5Report throughSep 30, 2026
6Share of grant period elapsed0.748
7Pace tolerance (+/-)0.1
8
9Budget lineApproved budgetQ1Q2Q3Q4Spent to dateRemaining% spentPace
10Personnel4200010500105001020031200108000.743On pace
11Fringe benefits8400210021002040624021600.743On pace
12Program supplies650090023001450465018500.715On pace
13Books for participants9000012006700790011000.878Ahead of pace
14Travel240015030020065017500.271Behind pace
15Evaluation consultant5000002500250025000.5Behind pace
16Indirect costs7000170017501800525017500.75On pace
17Total80300153501815024890058390219100.727On pace
18
19Lines off pace3
20Which linesBooks for participants, Travel, Evaluation consultant

How the formulas work

How much of the grant period has passed

B6=ROUND((B5-B3+1)/(B4-B3+1),3)

Dates are day numbers, so subtracting gives days. The +1 counts both the first and last day. Reporting through September 30 on a calendar-year grant means 273 of 365 days, or 74.8% of the period, have passed. That is the benchmark every line is compared with.

Spent to date and remaining

H10=B10-G10

G10 adds the four quarters with SUM, so empty future quarters simply count as nothing. Remaining is the approved budget minus spending to date. A negative Remaining means the line is overspent and may need a budget modification under your funder's rules.

Is each line on pace?

J10=IF(I10>$B$6+$B$7,"Ahead of pace",IF(I10<$B$6-$B$7,"Behind pace","On pace"))

Compares % spent with % of time elapsed, give or take the tolerance in B7 (10 points in the sample). Books (87.8%) is ahead of pace, while Travel (27.1%) and the evaluation consultant (50%) are behind. Behind is not always bad (an invoice can be late), but it is what funders ask about.

List the lines to explain in the report

B20=IFERROR(TEXTJOIN(", ",TRUE,FILTER(A10:A16,J10:J16<>"On pace")),"None")

FILTER keeps the line names whose Pace is anything other than On pace and TEXTJOIN joins them, giving you the list of variances to explain in your narrative. Needs Excel 2021, Microsoft 365 or Google Sheets.

Make it yours

FAQ

How do I make a budget vs actual report in Excel?

List each budget line with the approved amount, add a column for actual spending, and subtract to get the variance. Divide actual by budget for % spent. For a grant, compare % spent with the share of the grant period that has passed to see whether spending is on pace.

What does "behind pace" mean on a grant budget?

It means a line has spent less of its budget than the share of time that has passed, by more than the tolerance you set. It can signal a delayed activity, or money that may need to be moved or returned, depending on the funder's rules.

Can I track several grants in one workbook?

Yes. Keep one sheet per grant with this layout, then add a summary sheet that pulls each grant's totals with references like ='Grant A'!G17.